ePLDT is building the largest and most advanced data center in the country in a 5-hectare property in Sta. Rosa, Laguna.
VITRO Sta. Rosa will have an initial power capacity of 14MW in early 2024 and will further increase to 50MW once fully operational
This hyperscale facility is designed to be Rated-3 Certified and Rated-4 Ready and is equipped with at least three fiber routes to ensure network diversity, resilience and carrier-neutrality. Designed based on LEED standards, VITRO Sta. Rosa will implement the global-class sustainability practices in design, supply and building operations.
Events
This data center has timeline events listed. Typically events are related to M&A history, rebranding, capacity expansions etc.
2022, Q3 - Stage Change - Announced
Plans for PLDT's Sta Rosa data centre were first announced in February 2022
2022, Q3 - Stage Change - Under Construction
PLDT broke ground on the facility in March 2022
2025, Q4 - Stage Change - Operational
First phase of PLDFT's Sta Rosa site went live in April 2025
Pricing & Services
If you are looking for colocation, cloud, connectivity or other services in ePLDT VITRO Sta Rosa, other data centers in Santa Rosa or operated by ePLDT, please try our free quote service or reach out for a free consultation about your data center needs. We use a best effort process to qualify opportunities and route them to matching operators.
Advertisement
Nearest Data Centers
The below data centers are located closest to Pulong Santa Cruz.